Distribution Facility Expansion, Consolidation & Technology Upgrade

v3.7.0.1
Distribution Facility Expansion, Consolidation & Technology Upgrade
12 Months Ended
Jan. 28, 2017
Distribution Facility Expansion [Abstract]  
Property, Plant and Equipment, Schedule of Significant Acquisitions and Disposals [Table Text Block]
Distribution Facility Expansion, Consolidation & Technology Upgrade
During fiscal 2014, the Company began a significant operational expansion initiative with respect to overall warehousing capacity and new equipment and system technology upgrades at our Bowling Green, Kentucky distribution facility. During fiscal 2015, the Company expanded our 262,000 square foot facility to an approximately 600,000 square foot facility and moved out of the Company's leased satellite warehouse space. The updated facilities and technology upgrade includes a new high-speed parcel shipping and item sortation system coupled with a new warehouse management system to support our increased level of shipments and a new call center facility to better serve our customers. The new sortation and warehouse management system were phased into production through fiscal 2016. Total cost of the physical building expansion, new sortation equipment and call center facility was approximately $25 million and was financed with our expanded PNC revolving line of credit and a $15 million PNC term loan.
As a result of our distribution facility expansion, consolidation and technology upgrade initiative, the Company incurred approximately $677,000 in incremental expenses during fiscal 2016 related primarily to increased labor and training costs associated with the Company's warehouse management system migration. For fiscal 2015, we incurred approximately $1,347,000 in incremental expenses related primarily to increased labor, inventory and other warehousing transportation costs, training costs and increased equipment rental costs associated with: the move into the new expanded warehouse building, the move out of previously leased warehouse space and the preparation of our expanded facility for the new high-speed parcel shipping and item sortation system and upgraded warehouse management system.